Granite Ridge Builders
General Contractor · Lic. GC-118402
Statement of WorkSOW-HP-400
Statement of Work · Tenant Improvement

Suite 400 Tenant Fit-Out

Harbor Point · 600 Wharf Blvd, 4th Floor · Baltimore, MD 21202

Granite Ridge Builders, as lead general contractor, will deliver a complete interior fit-out of Suite 400 — demolition, framing, MEP, finishes, and close-out — for a professional-services tenant, on a 14-week schedule built around landlord and jurisdictional sign-offs. Each milestone is gated on the inspection or approval that releases it.

Contractor
Granite Ridge Builders, LLC
2200 Industrial Pkwy, Baltimore, MD 21230
Referred to herein as the "Contractor."
Client / Tenant
Whitfield & Crane LLP
Tenant of Suite 400, Harbor Point
Referred to herein as the "Client."
Contract Sum
$427,500
Duration
14 wk
Milestones
5
Substantial Completion
Sep 18, 2026
Issued under the AIA-form prime contract dated PC-2026-0211
Scope at a Glance Five inspection-gated milestones · 14 weeks
1
Demolition & Protection
Gate ▸ Suite cleared to slab; landlord demolition walk-through signed.
2
Framing & Rough-In
Gate ▸ Framing and MEP rough-in inspections passed; walls ready to close.
3
Drywall & MEP Trim
Gate ▸ Ready-for-paint sign-off; systems energized, tested, balanced.
4
Finishes Installed
Gate ▸ Architect's finish walk-through complete; all finishes to schedule.
5
Close-Out & CO
Gate ▸ Certificate of occupancy issued; punch list closed; keys handed over.
Drawing Set
A-2.04 Rev 3
Permitted TI set · Feb 6, 2026
Building Standard
Harbor Point
Work letter · Exhibit C of the lease
Code
IBC 2021
Baltimore City amendments · ADA
Suite Area
11,400 SF
Rentable · 4th floor · full demise
Project
Suite 400 Fit-Out
SOW No.
SOW-HP-400
Contractor
Granite Ridge Builders
Sheet
1 of 5
01

Scope of Work

The work the Contractor is responsible for — and the line the lease draws around it

The Contractor will perform a turn-key interior fit-out of Suite 400 to the approved tenant-improvement drawings: selective demolition, metal-stud framing and drywall, mechanical/electrical/plumbing rough-in and trim, ceilings, flooring, millwork, paint, and final close-out. All work conforms to the building standard, the lease work letter, and the permitted drawing set, and is delivered in five inspection-gated milestones.

In Scope
+Selective demolition of existing partitions, ceilings, and finishes per the demo plan.
+Metal-stud framing, insulation, and drywall for all new partitions and the demising wall.
+MEP rough-in and trim: HVAC distribution, power and lighting, and plumbing for the pantry.
+Finishes: ACT ceilings, carpet tile and LVT flooring, millwork, doors and hardware, and paint.
+Permits, inspections, punch-list completion, and close-out documentation.
Out of Scope
Furniture, fixtures, and equipment (FF&E) and their installation.
Tenant low-voltage cabling, AV, and security systems (by the Client's vendor).
Base-building systems, the core, and common-area work owned by the landlord.
Hazardous-material abatement, if discovered, handled by separate change order.
Design and architectural/engineering services beyond as-built record drawings.
Drawing Set
A-2.04 Rev 3Permitted TI set, dated Feb 6, 2026
Building Standard
Harbor PointTenant work letter, Exhibit C of the lease
Code
IBC 2021Baltimore City amendments; ADA-compliant
Suite Area
11,400 SFRentable, 4th floor, full-floor demise
Site Logistics & Access

Work is sequenced around an occupied building. The Contractor stages materials in the 4th-floor freight lobby, hoists via the freight elevator on landlord-scheduled slots, and protects the elevator cab, corridors, and adjacent suites. Loud demolition and core drilling run in landlord-approved after-hours windows; dust and noise controls stay up for the duration.

Coordination & Sequencing

Trades are sequenced demo → frame → rough-in → inspect → close walls → finish → punch, with a weekly coordination meeting and a two-week look-ahead schedule. Each inspection gate must clear before the wall is closed or the next trade mobilizes; failed inspections are re-walked within two business days at no schedule credit to the Client.

Assumptions, Permits & Dependencies

The permitted drawing set is final and the building permit is issued before Milestone 1 starts. The landlord provides freight-elevator access, after-hours work windows for loud demolition, and timely review of the work letter. The schedule assumes inspections occur within two business days of request; jurisdictional delays beyond that adjust the schedule one-for-one. Concealed conditions and abatement are handled via change order under the General Conditions on the final sheet.

Project
Suite 400 Fit-Out
SOW No.
SOW-HP-400
Initials
Sheet
2 of 5
02

Work Breakdown & Acceptance

By trade package — each "complete" only when its acceptance test is met
Standard of Completion
A trade package is complete only when its acceptance test is met and the governing inspection or architect's walk-through is signed. Work is performed to the permitted drawings, the building standard, and the manufacturers' published instructions; substituted materials require the architect's written approval. Each package is the gate for the matching milestone draw — no draw is released against incomplete or un-inspected work.
01DEMO
Demolition & Site Protection
Remove existing partitions, ceilings, and finishes to the demo plan; protect base-building systems, elevator lobby, and adjacent occupied suites.
Accept whenSuite cleared to slab and deck per plan; debris removed; landlord walk-through signed; no damage to base-building systems noted.
02FRAME
Framing, Drywall & Demising Wall
Metal-stud framing for all partitions and the rated demising wall, insulation, and drywall hung, taped, and sanded ready for finishes.
Accept whenFraming inspection passed; rated assemblies match the permit set; walls plumb within 1/8” over 10 ft; ready-for-paint sign-off by the architect.
03MEP
MEP Rough-In & Trim
HVAC distribution and controls, power, lighting and panels, and pantry plumbing — rough-in inspected, then trimmed out and commissioned.
Accept whenRough-in inspections (mechanical, electrical, plumbing) all passed; systems energized and tested; balancing report and panel schedules delivered.
04FINISH
Ceilings, Flooring, Millwork & Paint
ACT ceilings, carpet tile and LVT flooring, reception and pantry millwork, doors and hardware set, and full paint to the finish schedule.
Accept whenAll finishes installed to the finish schedule; surfaces clean and defect-free; hardware functional; architect's finish walk-through complete.
05CLOSE
Inspection, Punch List & Close-Out
Final jurisdictional inspection, punch-list completion, as-built record drawings, O&M manuals, warranties, and the certificate of occupancy.
Accept whenCertificate of occupancy issued; punch list closed and re-walked; as-builts, O&M manuals, and warranties delivered; keys handed over.
Project
Suite 400 Fit-Out
SOW No.
SOW-HP-400
Initials
Sheet
3 of 5
03

Schedule, Draws & Contract Sum

Five inspection-gated milestones over 14 weeks — each releases a progress draw
Stipulated Contract SumInclusive of labor, materials, permits, and the listed trade packages
$427,500
1WK 1–2
Demolition Complete
Jun 22 – Jul 3, 2026
Gate ▸ Landlord demolition walk-through signed; suite cleared to slab.
$42,750
Draw 1 · 10%
2WK 3–6
Framing & Rough-In
Jul 6 – Jul 31, 2026
Gate ▸ Framing inspection + MEP rough-in inspections passed.
$128,250
Draw 2 · 30%
3WK 7–9
Drywall & MEP Trim
Aug 3 – Aug 21, 2026
Gate ▸ Ready-for-paint sign-off; systems energized and tested.
$106,875
Draw 3 · 25%
4WK 10–12
Finishes Installed
Aug 24 – Sep 11, 2026
Gate ▸ Architect's finish walk-through complete; all finishes to schedule.
$106,875
Draw 4 · 25%
5WK 13–14
Close-Out & CO
Sep 14 – Sep 18, 2026
Gate ▸ Certificate of occupancy issued; punch list closed; retainage release.
$42,750
Retainage · 10%
Draw Cashflow — value released per milestone (Contract Sum $427,500)
$42.8k
$128.3k
$106.9k
$106.9k
$42.8k
Draw 1 · 10%Draw 2 · 30%Draw 3 · 25%Draw 4 · 25%Retainage · 10%
Payment
Progress draws are submitted on AIA G702/G703 with each accepted milestone, payable Net-30, less 10% retainage held and released at certificate of occupancy and punch-list close-out.
Change Orders
Concealed conditions, abatement, or scope additions are priced and approved by signed change order before the work proceeds; markup is 12% on cost. Inspection turnaround beyond two business days adjusts the schedule one-for-one.
Allowances
Finish allowances for flooring and millwork are carried in the sum; over/under is reconciled by change order at close-out. Loud work runs in landlord-approved after-hours windows.
Project
Suite 400 Fit-Out
SOW No.
SOW-HP-400
Initials
Sheet
4 of 5
04

Authorization to Proceed

Signed below, this SOW is incorporated into the prime contract
Project
Suite 400 Fit-Out
Contract Sum
$427,500
Duration
14 wk
Milestones
5

General Conditions

Change orders. Any change to the scope, schedule, or contract sum — including concealed conditions and abatement — takes effect only by written change order signed by both parties before the work proceeds. Field directives do not alter this SOW.

Governing contract. This SOW is incorporated into and governed by the prime contract referenced on the cover. Where this SOW and the prime contract conflict, the prime contract controls except as to scope, milestones, contract sum, and schedule, which this SOW controls.

Permits & inspections. The Contractor pulls and closes the building permit and coordinates all jurisdictional inspections. Substantial completion is achieved on issuance of the certificate of occupancy.

Insurance & lien. The Contractor maintains general liability and workers' comp per the prime contract and furnishes conditional and unconditional lien waivers with each draw.

Warranty. The Contractor warrants all work against defects in materials and workmanship for one year from substantial completion, manufacturer warranties passed through to the Client.

Safety & cleanup. The Contractor maintains an OSHA-compliant site, daily housekeeping, and dust/noise controls protecting occupied floors; the suite is broom-clean at each milestone and final-cleaned before the close-out walk. Damage to base-building or adjacent-tenant property is repaired by the Contractor at its cost.

By signing below, the named representatives confirm the scope, work breakdown, milestone gates, and draw schedule above and authorize the Contractor to proceed under SOW SOW-HP-400. Each signatory warrants they are authorized to bind their organization.
Contractor
Granite Ridge Builders, LLC
Printed Name
Title
Signature
Date
Client / Tenant
Whitfield & Crane LLP
Printed Name
Title
Signature
Date
This Statement of Work, SOW-HP-400, comprises five sheets and supersedes prior drafts upon signature by both parties.
Project
Suite 400 Fit-Out
SOW No.
SOW-HP-400
Contractor
Granite Ridge Builders
Sheet
5 of 5